There are 4 main work streams under the project:
- Code Base Deployment
- Data Migration
- Customized Requirements (Flutterwave Integration and Instant Swap)
- Knowledge Transfer and Training
1. Code Base Deployment
Target
- To deploy a new code base in 4 environments include, development, testing, pre-production and production.
- Quidax devops team should be trained and be able to deploy independently.
Task Breakdown and Schedule
https://docs.google.com/spreadsheets/d/1VR0wJ3ID6qVDqc5C9wT3mwvSMPmSYdcQVQ10kpBu-D4/edit#gid=1115838130
2. Data Migration
Target
- To migrate data from Quidax 2.0 to Quidax 3.0 without causing any impact to existing users when they use quidax 3.0 by our own data team.
- Migrated data must be reconciled by our own data team and functional verified by our own QA team.
Task Breakdown and Schedule
https://docs.google.com/spreadsheets/d/1xyXpE1EJ9lLiaP9dsUMAJw3r0ETMexmFGBXVyrJFP0U/edit?gid=1892194870#gid=1892194870
3. Customized Requirements
Target